Economic and market impact

Our core business and additional undertakings generate positive impulses in the Polish economy. We contribute significantly to the creation of added value, jobs, income for the population, and through the taxes we pay ─ we also contribute to the development of the region.

Stable operation of the national power system

We care about the safety and stable operation of the power system - today and in the future.

Being aware of the state of the national infrastructure and the challenges and trends that affect the development of the system, we make investments and conduct research and development works to ensure its stability and security.

Our activities help improve the operation of the NPS and optimize energy costs borne by the customers.

We run our business locally, purchasing from local Polish suppliers, thus having a positive impact on the development of the Polish economy.

Through the services provided, PSE supports the development of industry in Poland, creating the infrastructure and providing facilities for business development.
Key figures

Operation
of the
PPS system

49,238 MW

of installed capacity in the NPS in 2020

49,095 MW

of available capacity in the NPS in 2020

26,799 MW

maximum demand for capacity in the NPS in 2020, 295 MW higher than the corresponding figure for 2019, when the previous demand record was set

152,308 GWh

of gross domestic electricity production in 2020, down 4.07 percent from 2019

165,532 GWh

of national electricity consumption in 2020, a minimal decrease of 2.28 percent compared to 2019

138,163 MWh

of total energy consumption in 2020 by end users connected to the NPS

93,522 GWh

of electricity delivered from the transmission network to domestic customers of transmission services in 2020




System
operation
indicators

99,99%

electricity supply continuity index in 2020. The index level confirms the power supply reliability for all our transmission service buyers

124,35 MWh

ENS (index of Electricity Not Supplied by the system)

22.18 (minutes)

AIT (index of Average Interruption Time in the system)

1,40%

transmission network loss index in 2020

99,73%

transmission equipment availability index (DYSU) in 2020. It reached a high value with a reference value ≥ 97.5 percent.




Investments in numbers

PLN 1.1 billion

in capital expenditures incurred in 2020

160

network infrastructure investment projects implemented in 2021

PLN 14.2 billion

in capital expenditures planned until 2030

Power system management in Poland

GRI 103-2
Ensuring access to electricity requires an efficiently operating system that enables its seamless generation, processing, transmission and distribution. All the equipment connected to this system, together with consumers’ installations, form the national power system.
The power system belongs to a special type of critical infrastructure, as it determines the security of society, the economy and the state. This system is centrally controlled. The National Dispatching Center, the so-called dispatching service of PSE, is responsible for the operation of the Polish power system.
How does the power system operate?

GRI 103-1
The national power system (NPS) is formed by three subsystems responsible for specific tasks.
  • Electricity generation ─ the production of energy by generation sources, which - in the power system - are power plants, combined heat and power plants and distributed sources.
  • Transmission of electricity ─ is carried out through the transmission network in order to deliver energy to distribution networks or to customers connected to the transmission network. Electricity transmission is carried out by the transmission system operator whose functions are performed by PSE.
  • Distribution of electricity ─ the supply of electricity through distribution networks to institutional and individual consumers connected to this network. Electricity is distributed by distribution system operators.
Cross-border connections

The national transmission system operates:
  • ynchronously with the systems of continental European states ENTSO-E (formerly UCTE),
  • with dedicated power units of the Dobrotwór power plant of the Ukrainian system,
  • non-synchronously with the Swedish system via a DC submarine cable,
  • non-synchronously with the Lithuanian system through a DC back-to-back converter station.
Synchronous connections
Western border (Poland-Germany)
  • 400 kV Krajnik-Vierraden double-circuit line - the line operates in the transient mode (1 line circuit and two phase shifters on the German side connected in series),
  • 400 kV Mikułowa-Hagenwerder double-circuit line - with a phase shifter in Mikułowa.
Southern border (Poland-Czech Republic)
  • 400 kV Wielopole/Dobrzeń-Nosovice/Albrechtice double-circuit line,
  • 220 kV Kopanina/Bujaków-Liskovec double-circuit line.
Southern border (Poland-Slovakia)
  • 400 kV Krosno Iskrzynia-Lemesany double-circuit line.
Non-synchronous connections
Northern border (Poland-Sweden)
  • DC 450 kV Słupsk Wierzbięcin-Storno cable line with transmission capacity of 600 MW.
Eastern border (Poland-Lithuania)
  • 400 kV double-circuit line inter-operating with the Lithuanian system through a DC back-to-back converter station with a transmission capacity of 500 MW.
Other connections
Eastern border (Poland-Ukraine)
  • 220 kV Zamość-Dobrotwór single-circuit line inter-operating with dedicated generation units on the Ukrainian side (the interconnection only allows importing energy to Poland),
  • 750 kV Rzeszow-Chmielnicka single-circuit line - decommissioned.

Sweden

Northern border (Poland-Sweden)

DC 450 kV Słupsk Wierzbięcin-Storno cable line with transmission capacity of 600 MW.

Germany

Western border (Poland-Germany)

400 kV Krajnik-Vierraden double-circuit line - the line operates in the transient mode (1 line circuit and two phase shifters on the German side connected in series),

400 kV Mikułowa-Hagenwerder double-circuit line - with a phase shifter in Mikułowa.

The Czech Republic

Southern border (Poland-Czech Republic)

400 kV Wielopole/Dobrzeń-Nosovice/Albrechtice double-circuit line,

220 kV Kopanina/Bujaków-Liskovec double-circuit line.

Slovakia

Southern border (Poland-Slovakia)

400 kV Krosno Iskrzynia-Lemesany double-circuit line.

Ukraine

Eastern border (Poland-Ukraine)

220 kV Zamość-Dobrotwór single-circuit line inter-operating with dedicated generation units on the Ukrainian side (the interconnection only allows importing energy to Poland),

750 kV Rzeszow-Chmielnicka single-circuit line - decommissioned.

Lithuania

Eastern border (Poland-Lithuania)

400 kV double-circuit line inter-operating with the Lithuanian system through a DC back-to-back converter station with a transmission capacity of 500 MW.

Russia

Belarus

750kV

450 kV DC

400kV

220kV

DC back-to-back converter station

Phase shifter

Line subject to upgrade from 220 to 400 kV

Cross-border connection undergoing modernization

Radial line

Fig. Cross-border connections
GRI 103-2
Transmission system management in the NPS
The operation of the transmission network takes into account the needs of electricity consumers nationwide.
The current operational security of the power network is ensured by the dispatching services of the TSO and DSO as well as the operational services of generators and customers operating in a hierarchical system.
The national power system has the following hierarchy of dispatching services:
  • National Dispatching Center (KDM) – manages the operation of the 750, 400, 220 kV transmission network, as well as selected 110 kV lines of system importance,
  • Area Dispatching Center (ODM) – manages the operation of the transmission network and the switching operations of the 750, 400, 220 and 110 kV transmission network,
  • Central Dispatching Centers, Branch Dispatching Centers (CDM, OCD) – manage the operation of the 110 kV distribution network and switching operations in the distribution network of 110 kV and below.
The dispatching services of TSOs cooperate directly with the dispatching services of DSOs (Central Dispatching Centers, Branch Dispatching Centers) and with the operational services of power generation companies (Power Plant On-Duty Engineer - DIRE). This cooperation is carried out in accordance with the Transmission Network Code.
Organization of dispatching services in the country
Fig. Organization of dispatching services in the country
The cooperation of TSOs with TSOs of neighboring countries with respect to network operation is carried out in accordance with the terms and conditions set out in the ENTSO-E/UCTE network codes and conditions specified in bilateral agreements.
Balancing of power demand

GRI 103-2
The economic development of the country is associated with an increase in the power demand. This affects the need for having suitable generation and transmission capacities to ensure security of supply.

In order to provide the generation capacity necessary to meet demand as a transmission system operator, we implement a coordination planning process for different time horizons. This process includes annual, monthly, and daily coordination plans.

The schedule of activities related to the development of plans and the scope of forecast and published data is defined in the Transmission Network Code.

Coordination plans are designed to allow the levels of excess capacity available over forecast demand to be met as required during the assumed period. This is achievable by coordinating the repair and maintenance schedules of generating units and shutdowns of meshed network elements, taking into account plant and network constraints and planned inter-system exchange restrictions.
To ensure continuity of energy supplies and balance the system even under adverse conditions, we have a number of tools at our disposal during periods of peak electricity demand:
  • the capacity available in generation units that are not centrally dispatched units,
  • additional capacity at power plants in overload conditions, i.e. with more than nominal capacity (as part of system services),
  • contingency capacity supply from pumped storage power plants, which allow for short-term (2-4 hours) balancing of power demand (as part of system services),
  • dispatching capacity exchange with neighboring TSOs,
  • Demand Side Response service provided on behalf of the TSO, i.e. DSR.

Measures to ensure reliable operation of the transmission system, including reliability metrics

GRI 103-2 GRI 103-3
In order to ensure secure and economic operation of the system, in particular to ensure the required reliability and quality parameters of the power system operation, PSE purchases system services.
System Services:
  • Control System Services (RUS):
    • operational capacity reserve,
    • participation in primary control,
    • participation in secondary control,
    • under- or overload operation,
    • participation in automatic voltage and reactive power control;
  • Start-up service for Generating Units (start-up service);
  • Control system services as part of the contingency reserve:
    • contingency operation,
    • contingency cold reserve (service provided until the end of 2020),
    • reduction of demand upon order of the TSO (service provided until the end of 2020, new service - Contingency Consumption Reduction since 2021);
    • Availability service for non-Centrally-Dispatched Generating Units (GWS service).
    • National power system restoration service.
Control system services (hereinafter: RUS) and start-up service for generating units
Are provided by units dispatched by the Operator. TSOs enter into agreements for the provision of control system and start-up services with all generators owning Centrally Dispatched Generating Units. In 2020 PSE entered into 12 agreements to provide control system services, including the provision of start-up service.
The control system services as part of the contingency reserve
Are activated upon order of the TSO and are used for contingency capacity balancing in the entire NPS or - due to the network operating conditions - in its selected areas in order to ensure the security of NPS operation. In 2020, our organization had 2 contingency operation service agreements, 3 cold reserve contingency service agreements, and entered into 27 demand side reduction service agreements upon TSO order.
Dispatching services of non-Centrally Dispatched Generation Units
Are one of the TSO's tools necessary to ensure secure operation of the NPS and the generation of active and reactive power in individual "network areas" (nodes or areas gathering certain nodes). In 2020 PSE had 11 generating unit availability service agreements with 7 generators.
The national power system restoration services
Consist in ensuring readiness to start up a power plant without external power supply and permanent operation in the island mode as well as readiness to carry out TSO's instructions regarding starting up further power plants and increasing the size of the isolated system. These services are purchased by the TSO in case of a large system failure resulting in a blackout in the entire or a significant part of the NPS. In 2020 PSE had NPS restoration service agreements with 4 generators.

System operation reliability indices (ENS, AIT)


GRI 103-3
System operation reliability indices (ENS, AIT)
The indices describing the continuity of power supply and the duration of power interruptions ( ENS and AIT ) were calculated for the group of delivery points, which include end customers and electricity distribution system operators with one delivery point from the transmission network. Shutting down the delivery point of these customers results in an interruption of energy supplies from the transmission network.

To determine the reliability of network operation in accordance with applicable regulations, ENS and AIT indices for emergency outages are calculated.
In-house indicator ENS In-house indicator AIT

ENS and AIT indices for emergency outages*
   2020  2019  2018  2017  2016
ENS MWh  
0,00 439,34 0,00 125,22 0,00
AIT minutes  
0,00 81,47 0,00 20,72 0,00
* The ENS and AIT index values shown in the table were calculated for unscheduled (emergency) interruptions and outages and do not include scheduled interruptions and outages.
In 2020 and 2018, there were no events resulting in emergency power interruptions and outages to customers at delivery points from the transmission grid identified as above.

There was one emergency interruption resulting in no power to the customer in 2019. The interruption lasted approximately 36 hours and was caused by a spontaneous shutdown of the 110 kV line from which the customer drawing power from the transmission network is supplied. The immediate cause of the interruption was a ground fault due to a tree coming close along the line section.

In 2017, there was one emergency interruption that resulted in an approximately 3-hour outage of energy delivery to one customer supplied from the transmission network. This was due to an emergency manual shutdown of the power lines due to a bystander climbing on a 220 kV line pole. The shutdown of other equipment, lines and transformers associated with the site was dictated by safety concerns.

Low levels of the ENS and AIT indices demonstrate a high level of operational reliability of the transmission network managed by PSE, as well as to the reliability of power supplies to customers connected to that network.
In-house indicator ENS In-house indicator AIT

ENS and AIT indices for all outages (planned and emergency)*
   2020  2019  2018  2017  2016
ENS MWh  
124,35 601,26 264,24 671,64 425,10
AIT minutes  
22,18 111,50 45,77 111,15 84,44
* The values of ENS and AIT indices shown in the table have been calculated for emergency and scheduled outages resulting from the necessary repair and maintenance works of transmission grid elements that supply customers.
The persistently low values of ENS and AIT indices have a positive impact on the confidence of customers connected to the transmission network. The reduction of the number and duration of planned outages of the supply of electricity to customers results, among other things, from the implementation of a system to optimize the schedule of repair and maintenance works of transmission network elements supplying the customers. The shutdowns in the case of scheduled outages are carried out by PSE at times agreed with the customers - usually during periods of no energy consumption as declared by the customers. As a result, during outages, customers adjust their demand or use other methods of supplying electricity (e.g., from the DSO network).
In-house indicator
Electricity supply continuity index
To determine the continuity of electricity supplies, the so-called WCD index is calculated.
Maintaining the supply continuity indices at a high level is the result of the TSO's operation and maintenance policy for transmission assets.

The amount of electricity not supplied to transmission service customers during the year was determined taking into account interruptions in energy supplies to customers - both scheduled and unscheduled. The index used in the calculation of the total amount of electricity supplied from the transmission network during the year is the volume of electricity taken from the transmission network at all delivery points by end customers and DSOs connected to the transmission network.
2016-2020 WCD index values are provided in the table below.
Electricity supply continuity index*
  2020 2019 2018 2017 2016
Electricity supply
continuity index*)
99,9999 99,9994 99,9997 99,9993 99,9995
* The supply continuity index defines the certainty of supplies to all customers connected to the transmission network.

Maintaining the supply continuity indices at a high level is the result of the TSO's operation and maintenance policy for transmission assets.
GRI 103-3
Actions taken by PSE to maintain continuity of electricity supplies to customers:
  • Preparation of coordination plans for network works in the long and short term horizons. The work schedules for both the operation and maintenance of network elements and generating units are planned in such a way as to ensure that the required levels of surplus capacity available over the forecast demand are met over the assumed period and that the required criteria for safe operation of the network, including the reliability criterion (n-1), are met;
  • Development and implementation of a uniform operating model allowing for cyclic, standardized and measurable assessment of the technical condition of equipment and its operating environment. Thanks to these actions, the most worn out and oldest elements of network assets - potential sources of emergency and disturbance conditions - are preventively replaced;
  • Implementation of the operating services development program. It allows for continuous improvement of the competence of our own operating services, including those performing work in the field;
  • Taking investment activities. Optimizes the load on transmission lines and eliminates overload conditions on transmission system components;
  • Systematic standardization of network equipment and creation of a storage base. It allows to make necessary replacements quickly and in a financially optimal way;
  • Working closely and making arrangements with transmission service customers at every stage, i.e. from planning to implementation.
Index of electricity losses in the transmission process

GRI EU12
Electricity losses in the transmission process, specifying causes of losses
  2020 2019 2018 2017 2016
Technical losses MWh 1 457 807 1 476 221 1 611 270 1 669 042 1 684 995
Non-technical losses (e.g. illegal consumption of electricity) 0 0 0 0 0
Transmission losses as a percentage of total energy supplied to the system
(official data G.10.7)*
1,40 1,38 1,48 1,60 1,62
* The value does not include electricity for substation auxiliaries.
Electricity losses in the transmission process in the transmission network result from technical losses, i.e. losses caused by physical phenomena in the network (e.g. load losses). They depend on many factors including wind unit generation, cross-border exchanges, equipment condition and weather conditions.

The year 2020 was exceptional in terms of balancing the national power system. The COVID-19 pandemic resulted in reduced demand for electricity in the country, causing lower loss volumes relative to 2019. Despite lower flows in the transmission network, the loss ratio was able to be maintained at a similar level and was 1.40 percent for 2020.

Physical security of critical infrastructure and a coherent protection system

GRI 103-1
We are an enterprise of strategic importance to national security. Our company is:
  • a critical infrastructure operator,
  • the owner of facilities subject to mandatory protection,
  • the owner of facilities of particular importance for the safety and defense of the state,
  • an enterprise of particular economic and defense importance.
Certain tasks and responsibilities have been imposed on PSE in connection with these functions.
As an operator of critical infrastructure, PSE is required to ensure the protection of the company's facilities1. In accordance with the National Program for Critical Infrastructure Protection, this obligation is understood very broadly and includes activities aimed at ensuring physical, technical, personal, ICT and legal security, as well as ensuring continuity of operations and the ability to restore critical infrastructure.
GRI 103-2 GRI 103-3
The Company is required to develop and update:
  • Critical Infrastructure Protection Plans - agreed with voivodeship governor, voivodeship chiefs of the Police, voivodeship chiefs of the State Fire Service, voivodeship inspectors of building control office and the minister in charge of energy and approved by the Director of the Government Security Center
  • Protection Plans - approved by regional Police chiefs and directors of the Regional Headquarters of The Internal Security Agency (ABW) (with respect to anti-terrorist annexes).
PSE is obliged to cooperate and exchange information with public administration authorities. In particular, we cooperate with the Government Security Center, the Ministry of Climate and Environment, the Ministry of State Assets, the Internal Security Agency, the Police, and provincial and local government administrations in this regard. Our company has also signed agreements on cooperation and information exchange with voivodeship and county authorities, where PSE facilities are located.

As the owner of facilities of particular importance for national security and defense and an entrepreneur of particular economic and defense importance, in accordance with the provisions of law2 we also perform tasks for national defense.
In order to ensure a high level of technical protection for PSE facilities, the Technical Protection Department was established within the structure of the Security Department, the task of which is to build up in-house expertise in this area and - ultimately - to reduce the costs of external service agreements related to the maintenance of these systems. At present, the process related to reviews of individual elements of technical protection systems operating at all substations is underway in order to check their technical condition and determine further necessary repair or investment activities. The review process associated with the technical protection systems at substations will last until the end of 2021.

[1] Such obligations are imposed on PSE under the Act of 26 April 2007 on crisis management, the Act of June 10, 2016 on anti-terrorist activities, the Act of March 18, 2010 on the special powers of the minister responsible for state assets and their exercise in certain capital companies or capital groups operating in the electricity, oil and gas fuel sectors, and the Act of August 22, 1997 on the protection of persons and property.
[2] The scope of these tasks is regulated by: the Act of November 21, 1967 on common obligation to defend the Republic of Poland and the Act of August 23, 2001 on organizing tasks for national defense carried out by entrepreneurs.

Development of the transmission system

GRI 103-1
The basis for the sustainable development of the national economy is to provide the necessary amount of electricity to all consumers. We are committed to ensuring that the transmission system provides a reliable electricity supplies both now and in the future. It is our responsibility.
Transmission network development plan

GRI 103-2
The Transmission Network Development Plan (PRSP) defines transmission network development projects, the implementation of which is expected to ensure that the national demand for capacity and electricity is met in the long term. The main factors influencing the directions of the transmission network development include: the increase in electricity demand, the development of generation sources, and the need to expand cross-border connections.
The 2021-2030 PRSP continues transmission network development directions included in the 2018-2027 PRSP. The strategic objective of PSE is to build a backbone power network based on 400 kV lines capable of adapting to the planned NPS development scenario, including in particular the development of the generation sector.
The analytical process to identify required infrastructure needs has changed significantly from the previous PRSP. An improved methodology for mapping the power system and its processes was developed and used. It included market analyses using the European market model, which resulted in a forecast of cross-border exchange between Poland and neighboring countries. In the tools and methods used, the time granularity was significantly increased, the stochastic nature of the NPS processes and the impact of weather variability on the power system operation were taken into account. Special emphasis was placed on the integrity and consistency of the quantities, databases, and assumptions used.
GRI 103-3
In preparing the 2021-2030 PRSP, legal considerations resulting from the following were taken into consideration:
  • concept of spatial development of the country,
  • voivodeship spatial development plans,
  • Poland's Energy Policy,
  • ENTSO-E TYNDP 2018 10-Year Development Plan,
  • erformance of connection agreements and specified conditions for connection to the transmission network,
  • performance of other obligations, including arrangements with the DSO,
  • EU regulations.
In the Development Plan for Meeting Current and Future Electricity Demand for 2021-2030, we have planned 215 investment tasks for the expansion and modernization of the transmission network. The estimated value of the planned outlays for the implementation of all investments for this period amounts to approximately PLN 14.2 billion, and their annual breakdown (in million PLN) is presented in the table below:
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
1457 1788 1415 2080 1269 1136 1200 1125 1451 1238
Implementation of the planned investment projects will contribute to the creation of measurable effects.
Systemic effects to be achieved as a result of the investments by 2030.
Type of effect Value
Increase in length of 400 kV line circuits [km] of which: 3 701
new lines 4 349
lines being decommissioned 648
Increase in length of 220 kV line circuits [km] of which: -378
new lines 258
lines being decommissioned 636
Length of 400 kV line circuits being retrofitted [km] 1 723
Length of 220 kV line circuits being retrofitted [km] 1 373
Increase in 400/220 kV transformation capacity [MVA] of which: 1 440
new transformers 2 500
transformers being decommissioned 1 060
Increase in 400/110 kV transformation capacity [MVA] of which: 10 170
new transformers 10 920
transformers being decommissioned 750
Increase in 220/110 kV transformation capacity [MVA] of which: 2 460
new transformers 7 490
transformers being decommissioned 5 030
Increase in reactive power compensation capacity [MVar] of which:  
new reactors 1 750
new capacitor banks 1 200

Improving the infrastructure investment implementation model

Network investment portfolio

GRI 103-2
In order to implement investments more efficiently, PSE periodically updates the Investment Portfolio, which is one of the main tools for managing investment projects.

The portfolio is a collection of network infrastructure investment projects grouped into investment programs. The projects entered into it are subject to grouping, categorization, prioritization and determination of the order of their implementation, taking into account in particular the system conditions related to the possibility of the required outages of transmission network elements. In exceptional cases, elements other than network infrastructure may be included in the Investment Portfolio.
All investment projects included in the Network Investment Portfolio are grouped into investment programs based on:
  • strategic importance - strategic programs,
  • locations and interdependencies of projects - area programs,
  • the nature of works supporting the implementation of other investment projects (e.g. investor’s deliveries, formal and legal issues).
Strategic programs

Portfel inwestycji sieciowych obejmuje sześć programów strategicznych oraz cztery obszarowe.
Program 1.
The strategic program "Power output system from the Kozienice Power Plant and improvement of power supply conditions in north-eastern Poland": 13 investment projects, PLN 1,053,760 thousand in total contracted budget.
Program 2.
The strategic program "Power output system from the Turów Power Plant and improvement of power supply conditions in south-western Poland": 16 investment projects, PLN 541,396 thousand in total contracted budget.
Program 3.
The strategic program "Power output system from the Dolna Odra Power Plant and RES , including improvement of power supply conditions in north-eastern Poland": 13 investment projects, PLN 650,403 thousand in total contracted budget.
Program 4.
The strategic program "Power output system from RES and improvement of power supply conditions in the northern Poland - eastern part": 24 investment projects, PLN 1,630,026 thousand in total contracted budget.
Program 5.
The strategic program "Power output system from the Bełchatów Power Plant and improvement of power supply conditions in central, eastern and north-western Poland": 30 investment projects, PLN 968,201 thousand in total contracted budget.
Program 9.
Strategic Program "Building submarine connections and energy storage facilities." 2 investment projects, no contracted investments.
Area programs

Program 6.
“North” Area Program: no investment projects are currently assigned under the program.
Program 7.
“South” Area Program: 22 investment projects, PLN 447,567 thousand in total contracted budget.
Program 8.
Area Program "Formal Completion of Investments." 14 investment projects, projects after the 6th decision gate.
Program 10.
“Investor's Deliveries” Area Program: 17 investment projects, PLN 463,195 thousand in total contracted budget.
Program 11.
The strategic program "Power output system from RES and improvement of power supply conditions in the northern Poland - western part": 9 investment projects, PLN 375,592 thousand in total contracted budget.

Key figures
as of June 30, 2021

160

projects

in strategic and area programs, including 84 already contracted

PLN 6,13

billion

total contracted budget of projects in the Network Investment Portfolio

25

contractors

construction, supply and service

Impact on employment in various sectors of the economy and on Poland's economic growth

GRI 103-2
The vast majority of the ongoing investments included in the network investment portfolio are projects with priority 1 assigned.
Examples of priority investments implemented under investment programs

The portfolio of network investments includes six strategic and four area programs.

      • Strategic Program 1. Power output system from the Kozienice Power Plant and improvement of power supply conditions in north-eastern Poland
        The objective of investment projects included in the Program 1 is to ensure reliable power output from the Kozienice Power Plant following its extension with a new 1000 MW power unit and to improve the reliability of power supply in the northern and north-eastern parts of the National Power System and Warsaw agglomeration.

      • Strategic Program 2. Power output system from the Turów Power Plant and improvement of power supply conditions in south-western Poland
        The purpose of investment projects included in the Program 2 is to ensure reliable power output from the Turów Power Plant following its extension with a new 480 MW power unit and to improve the reliability of power supply in the south-western part of the National Power System, specifically for the largest recipient in this area - Kombinat Górniczo-Hutniczy Miedzi (KGHM). The investment projects included in the Program 2 also have a significant impact on the possibility of energy transmission and power supply in the northern areas of the country and on the possibilities of cross-border exchange in the synchronous section (connections between Poland and Germany, the Czech Republic and Slovakia) - especially in the import direction.

      • Strategic Program 3.Power output system from the Dolna Odra Power Plant and RES, including improvement of power supply conditions in north-eastern Poland
        The implementation of investment projects included in the Program 3 is expected to ensure reliable power output from the Dolna Odra Power Plant as well as from the wind farms and photovoltaic sources existing or planned in the northern part of the country and to improve the reliability of power supply in the north-western part of the NPS. These investment projects also have a significant impact on the possibility of cross-border exchange in the synchronous section (connections between Poland and Germany, the Czech Republic and Slovakia), especially in the import direction.

      • Strategic Program 4. Power output system from RES and improvement of power supply conditions in the northern Poland - eastern part
        The purpose of investment projects included in Program 4 is to ensure reliable power output from wind farms located in the northern part of the country, to improve the reliability of power supply in the northern part of the NPS and the possibility of cross-border exchange with the Swedish and, in the future, Lithuanian power systems.

      • Strategic Program 5. Power output system from the Bełchatów Power Plant and improvement of power supply conditions in central, eastern and north-western Polandi
        Implementation of the investment projects included in the Program 5 is expected to ensure reliable power output from the Bełchatów Power Plant and improve the reliability of power supply in the central, eastern and north-western parts of the NPS, including the Łódź and Szczecin agglomerations. The investment projects included in the Program 5 also have a significant impact on improving the reliability of telecommunications and communications infrastructure. Some of these are local in nature, primarily related to the expansion and retrofit of existing network assets.

      • Area Program 7. South
        The purpose of implementing the investment projects included in the Program 7 is to ensure the reliability of operation of the transmission network in the southern part of Poland located below the conventional Warsaw-Poznan line. These are local investment projects, mainly related to the expansion and modernization of existing network assets.

      • Area Program 10. Investor's deliveries
        The purpose of implementing the projects included in the Program 10 is to ensure investor's deliveries of autotransformers and reactors for implemented network investment projects as well as deliveries of selected equipment and instrumentation for investment projects and operating tasks.
        These projects - with regard to the supply of circuit breakers, isolating switches, busbar protection, feeder protection, optical ground wires (OPGW), transformers, phase conductors, MTS and SSiN (Control and Monitoring System) circuit-breaker modules - are intended to optimize the company's purchasing processes and reduce investment and operating expenses by achieving the economies of scale.


PLN 1,1
billion

capital expenditures
incurred in 2020.

Tab. Planned and incurred capital investments in 2020.
  Task name PERFORMANCE
[PLN thous.]
PERFORMANCE
[PLN thous.]
Items PZI   2020 2019
1 3 7 7
I Information and communication technology 131 753,8 119 611,5
II Construction, extension and modernization of substations and power lines 921 393,9 1 513 674,6
III List of investment projects scheduled for conditional or subsequent execution 1 326,0 111,8
IV Buildings and structures 5 064,3 15 883,8
V Purchase of finished capital goods 29 765,6 14 918,0
VI Purchase of network facilities and regulation of legal status of real properties 1,4 6,8
VII Reserve 19 332,6 5 701,7
IN TOTAL Including the reserve 1 109 596,7 1 669 908,2

Strona wykorzystuje pliki cookies. Używamy informacji zapisanych za pomocą cookies w celach statystycznych oraz w celu dostosowania serwisu do indywidualnych potrzeb użytkowników. W przeglądarce internetowej można zmienić ustawienia dotyczące cookies. Więcej o plikach cookies i o ochronie Twojej prywatności read here